Every AI data center is the same deal: a site with power on a date, one tenant’s signature, borrowed money, and a building wrapped around someone else’s chips.

Worked example
100 MW of racks, in four halls of 25 MW
Holds
about 740 racks, 53,000 GPUs
The building
about $1.1 billion: 23% of the bill
The chips in it
about $3.7 billion: the other 77%
Rents for
about $144 million a year, power on top
Slowest part
the grid connection: over four years

Point at a layer to name it. Click to open it. Tap a layer to open it. Scroll to follow one from an empty field to the first rent.

The campus, layer by layer

The building

A steel frame, wall panels and a roof. Structurally it is simpler than a high-rise.

This part goes up fast. What is slow, and costly, is everything that goes in and around it: electrical work alone is 45% to 70% of construction cost.

The floor has to carry about 1.5 tonnes per rack.

Owned by
The project company, which is the landlord
Paid for with
Equity, a construction loan, then bonds
Building, power and cooling together
about $11.3M per MW, 2026 average

Who builds it: DPR Construction, Turner, Holder, Mortenson.

The network

Fiber from the outside world meets the site’s own in one room. From there it runs over every row.

There are two networks. Inside a rack, copper joins 72 GPUs into one machine. Between racks, optical fiber runs through switches to join them into a cluster.

Every optical link needs a laser, and the lasers are in short supply.

Owned by
The tenant, with the chips
Inside the rack
Nvidia’s NVLink, on copper
Between racks
InfiniBand or Ethernet, on fiber

Who makes the switches: Arista, Broadcom, Nvidia, Celestica.

Chips and servers

About 740 racks, each holding 72 GPUs. This is what the building exists to power and cool.

It is 77% of the bill, and usually someone else’s. The tenant buys the racks and installs them. The landlord owns the shell, the power and the cooling.

The clocks do not match. Chips age out in about five years. The power gear under them lasts thirty.

Owned by
The tenant, or a company that leases them to it
Paid for with
The tenant’s cash, or a loan against the chips
Lasts
about 5 years
One rack draws
135 kW

Who makes them: Nvidia, Foxconn, Quanta, Supermicro, Dell.

Cooling plant

Chillers outdoors, a loop of water past every hall, and pump units inside that feed the racks.

A rack sends about 90% of its heat into liquid and 10% into the room’s air. That liquid runs in a sealed loop: it is filled once, and not used up.

Water is only consumed outdoors, and only at sites that shed their heat by evaporation. The fights over water are about those.

Owned by
The landlord
Heat carried off by liquid
about 90%
One pump unit in a row serves
up to 8 racks

Who makes chillers and pump units: Vertiv, Schneider Electric, Trane, Carrier, nVent.

Power gear

A transformer steps the voltage down. Switchgear routes it and cuts it off if something shorts. Batteries and generators carry the hall through a power cut.

This is the slow part to buy. Quotes for transformers and switchgear run 52 to 150 weeks.

It is also the part that keeps its value: power gear lasts 30 to 35 years, so debt secured on it is the safe kind.

Owned by
The landlord
Lasts
30 to 35 years
Quoted wait
52 to 150 weeks

Who makes it: Schneider Electric, Eaton, Vertiv, ABB, Siemens.

On-site power

Engines or turbines burning gas from a pipeline, with batteries to steady them. Power without the wait for a grid connection.

It costs more per unit of energy than the grid, and that rarely decides it: the dearer power adds only a few cents to an hour of a GPU’s time.

It can be bought, or rented. A power-as-a-service provider owns and runs the plant and sells electricity under a long contract, which keeps the plant off the developer’s books.

Owned by
The landlord, or a power company under contract
Costs, at most
about $3,500 per kW
Share of new US data centers from 2028
over half

Who makes the generators: GE Vernova, Siemens Energy, Caterpillar, Wärtsilä, Bloom Energy.

Grid connection

A substation that taps the high-voltage line, and the utility’s written promise of megawatts on a date.

The promise is the asset. A site is worth what its signed, dated utility agreement says, and lenders underwrite exactly that.

At 100 MW nothing is borrowed: the project builds its own substation.

Owned by
The landlord, and beyond the fence the utility
A connection in a primary market takes
over four years
The highest-voltage transformers take
4 to 5 years

Who makes large transformers: Hitachi Energy, Siemens Energy, HD Hyundai Electric, Hyosung Heavy.

The land

A field beside a power line, a gas pipeline and a fiber route. The cheapest layer, and the first one secured.

The usual move is an option, not a purchase: a fee to hold the site for a year or two, with the right to buy at an agreed price.

Some owners prefer a long ground lease, or a stake in the project.

Owned by
The project company, or leased from the landowner
Secured with
An option

01 The United States

Data centers go where the power is

A data center is built wherever electricity can be had on a date. Land is easy. A hundred megawatts, as much as a small city draws, is not.

You cannot rent your way there. Northern Virginia, the largest market in the world, had 10.8 MW left to lease in the first half of 2026.

Northern Virginia is full

The largest data center market in the world, with 10.8 MW left to lease. A new campus wants ten times that.

So it goes where the power is

The campus lands wherever 100 MW can be had on a date. Here, west Texas.

The largest campuses now going up

Not one of them is in an old data center market.

Left to lease in Northern Virginia, first half of 2026
10.8 MW
A grid connection in a primary market takes
over four years

Who needs the megawatts: Microsoft, Alphabet (Google), Amazon, Meta, Oracle.

02 A field, somewhere with power

What a 100 MW site needs

Five things, in one place. The search starts from a map of power lines, not a map of land: utilities publish how much room their lines have, and grid operators publish who is already waiting.

The commonest shortcut is an old industrial site, which already has a substation and a connection. This one is a field with all five. Scroll down the list.

  1. Land: 50 to 100 acres. Half an acre to an acre for every megawatt, going by the largest campuses. This field is 130 acres, which leaves room to grow.
  2. Power: 125 MW. To run 100 MW of racks a site draws about 125 MW, as much as a small city. That takes a high-voltage line with room to spare, and a substation of your own.
  3. Gas: 25 million cubic feet a day. Only if the site will make its own power. A plant this size burns about 25 million cubic feet a day, so it needs a large pipeline close by, with that much to spare.
  4. Fiber: two separate routes. Long-haul cable, which tends to follow roads and railways. Distance hardly matters: a model in training does not care how far away it is.
  5. Water: little. Less than most people think. The loop that cools the chips is filled once and sealed, so the creek matters most as a flood line to build clear of.
Cash to hold a site like this while it is checked
a few million dollars
What gets built on it, chips included
about $4.9 billion

The site is invented, to show the parts. They are drawn the size real ones are.

03 The same field

Audit the site: eight checks

A site is put to eight questions, in the order they most often end a deal. If the first two hold, most of the rest can be solved.

  1. The power is real. A written commitment from the utility, with megawatts and a date. Lenders underwrite exactly this.
  2. The land can be controlled. And zoning allows a data center on it.
  3. The community will not fight it. Check for talk of a moratorium before spending money.
  4. Water and cooling. The loop that cools the chips is filled once and sealed. Water is only used up if heat is shed outdoors by evaporation, so ask how this site will shed it.
  5. Fiber. Large routes nearby, or a cheap way to bring them in.
  6. The ground. No flood zone, soil that carries heavy buildings, room to grow.
  7. Labor. Electricians and contractors within reach.
  8. Money terms. The price of power, tax breaks, and who pays for grid upgrades.

04 The landowner’s kitchen table

Reserve the land with an option

The usual move is to pay the owner a fee to hold the site for a year or two, with the right to buy at an agreed price. In that window the checks are run. If one fails, the developer walks away and loses only the fee.

The paper comes in three steps: a confidentiality agreement, a one-page letter of intent that binds nobody, then the option itself.

A landowner who knows what the site is worth may prefer a long ground lease, or a share of the income, to a single payment.

05 The utility, and the grid operator

Get the power committed in writing

A site is worth what its signed, dated utility agreement says. First the utility studies whether its lines and substations can carry the load, for a fee. Then it commits megawatts and a date.

Texas asks at least $100,000 for the study, and proposes $50,000 a megawatt of security on top.

Then comes the queue. Texas has about 474 GW of requests waiting, roughly nine-tenths of them data centers.

Bottleneck 1: Power on a date. A grid connection in a primary market takes over four years on average.

Waiting to connect in Texas
about 474 GW
Security before the study, at 100 MW
about $5 million

06 Back on the site

Power: the grid, or your own plant

There are two routes to 100 MW. Many projects take both: gas first, as a bridge, and the grid later.

From 2028, SemiAnalysis expects over half of new American data centers to make their own power. In 2025 it was under 7%.

The gridYour own plant
The waitOver four yearsAbout two
Power costs, a MWh$55 to $115$100 to $165
Tight spotBig transformersTurbines, air permit

The plan, on the ground

Four halls of 25 MW. Now for where the power comes from.

Route A: the grid

Build a substation and tap the line. The cheapest power there is, after a long wait.

Route B: make it yourself

A row of gas engines and a bank of batteries. Faster, and dearer.

Often both

Gas first, as a bridge. The grid later.

Who makes the generators: GE Vernova, Siemens Energy, Wärtsilä, Bloom Energy.

07 County hall, then the state capital

Permits: who has to say yes

Even off the grid, several parties must give permission. Making your own power saves only the utility’s queue.

  1. The county or city: zoning. Is a data center allowed on that land at all? Most fights happen here.
  2. The county again: building and electrical permits. With inspections before anything is switched on.
  3. The state: an air permit. If gas is burned on site. Often the slowest of the five.
  4. Water. If the cooling uses it.
  5. The pipeline company. To connect the site and guarantee the fuel.
Local ballot measures on data centers, 3 November 2026
40 of 41 went against them

Rules differ by state and county. This is a map, not legal advice.

08 The deal

The deal: six parties, in order

A newcomer brings one thing, the powered site. Everyone else brings money, and the lender’s arrives fifth.

  1. Lock up the site and the power. With an option. It is cheap, and it is the developer’s whole stake.
  2. Bring in an equity partner. Usually an infrastructure fund. It puts up the risky early money, and takes most of the ownership.
  3. Spend the early money. Utility deposits, equipment deposits to hold a delivery slot, engineering, permits. Typically 5% to 10% of the project’s capital.
  4. Sign the tenant. One lease, for the whole site or a large phase.
  5. Close the construction loan. The equity goes in first. The lender releases money in stages as work is inspected.
  6. Build, test, hand over. Hall by hall. Rent starts with each handover.
  7. Refinance, or sell. Into cheaper long-term debt, or to a buyer.

Abilene, Texas: 1.2 GW, for OpenAI

  • Landowner: Lancium, which also manages the power
  • Developer: Crusoe
  • Equity partner: Blue Owl and Primary Digital
  • Tenant: Oracle, renting it on to OpenAI
  • Lender: JPMorgan: $9.4 billion of loans
  • Builders: Crusoe, which builds its own

Hyperion, Louisiana: 2 GW at first, for Meta

  • Developer: Meta itself
  • Equity partner: Blue Owl, which owns 80%
  • Tenant: Meta, on four-year terms it can walk from
  • Lender: Bond buyers: $27.3 billion at 6.58%, to 2049

River Bend, Louisiana: 245 MW, for Anthropic

  • Developer: Hut 8, a former bitcoin miner
  • Tenant: Fluidstack, renting it on to Anthropic
  • Lender: Bond buyers: $3.25 billion at 6.19%
  • Backstop: Google, which guarantees the rent

Polaris Forge, North Dakota: 400 MW, for CoreWeave

  • Developer: Applied Digital, once a host for bitcoin miners
  • Equity partner: Macquarie: $5 billion, at 12.75% plus 15% of it
  • Tenant: CoreWeave: about $11 billion over 15 years

Frontier, Texas: 1.4 GW, for OpenAI

  • Developer: Vantage
  • Tenant: Oracle, renting it on to OpenAI
  • Lender: JPMorgan and MUFG: $38 billion, with a sister site
  • Builders: Among them Jenbacher: over 500 gas engines

Childress, Texas: 750 MW, for Microsoft

  • Landowner: IREN
  • Developer: IREN, once a bitcoin miner. It owns the chips too
  • Tenant: Microsoft: $9.7 billion over five years, 20% up front

09 One contract

The lease: rent by the kilowatt

One tenant usually leases the whole site, or a large phase of it, before anything is built. That signed lease is what a lender will lend against.

It rents power, not floor space: about $100 to $150 for every kilowatt it reserves, every month, for 10 to 15 years, rising about 3% a year.

The landlord provides the building, the power and the cooling. The tenant brings its own chips, and pays the electricity bill on top.

Signed, before anything is built

No rent yet. It starts when the first hall is handed over.

Year 1: $144 million

Twelve months of rent.

15 years: $2.7 billion

The pale bars are what the building cost: the first seven years of rent pay for it. The lease is worth 2.4 times the building.

In Northern Virginia, asking, a kilowatt a month
$160 to $185

Who signs, most often: Microsoft, Amazon, Oracle, Meta.

10 The bill for 100 MW

The cost: 23% building, 77% chips

The building, with all its power and cooling gear, averages $11.3 million a megawatt in 2026: about $1.1 billion for 100 MW.

The racks that fill it cost about $3.7 billion more. So of every $4 spent, about $1 goes on the building and $3 on the chips inside it. A different party usually pays for them.

$1.13 billion: the building

With all its power and cooling gear. 113 blocks.

$3.74 billion: what goes inside

740 racks of chips and servers. 374 blocks, and usually someone else’s money.

23% building, 77% chips

Of every $4 spent, about $1 is the building and $3 is the chips inside it.

The building’s share of the whole bill
23%
Chips and servers, per MW
about $37 million
Electrical work’s share of the building
45% to 70%

One block is $10 million.

11 The lender’s office

The loan: 65% of the building

With the lease signed, a lender will cover 60% to 80% of the building’s cost: here 65%. The equity partner puts in 33% and the developer 2%. The loan runs 12 to 36 months, and is made to a company set up only to own this project.

Lenders check three things: the tenant’s credit, the utility’s written commitment, and whether the switch-on date is realistic.

$1.13 billion to find

The building, before a single chip.

65%: the loan

$735 million, lent against the lease. It is paid back first.

33%: the equity partner

$376 million from an infrastructure fund. It goes in before the lender’s money does.

2%: the developer

$20 million of its own cash. What it really brings is the site.

Meta’s way: 90% borrowed

Its Hyperion campus cost about $30 billion. A company owned 80% by Blue Owl borrowed $27 billion of it, and Meta rents the campus back.

Borrowed for Meta’s Hyperion campus
90%

Banks that arrange the loans: JPMorgan, Morgan Stanley, MUFG, Goldman Sachs.

12 A calendar, from today

Order the equipment years ahead

The building is quick. The equipment is not. So the developer orders the slow parts itself, before the contractor is even hired.

Suppose all of it is ordered today. Scroll to see when each thing arrives.

Bottleneck 2: The slow equipment. Money cannot hurry it: a deposit only holds a place in a factory’s queue.

Ordered today

Everything on this floor is ordered on the same day, at the end of 2026.

Who makes the slowest of it: Hitachi Energy, Siemens Energy, GE Vernova, Schneider Electric, Eaton.

The waits are the middle of the ranges quoted in 2026. The building’s is for one built the usual way.

13 Two halls, started the same day

Modular: built in a factory

The usual way, called stick-built, fits every part by hand on site. A modular data center is built in a factory, as finished sections of power, cooling and rack space, and trucked in.

Crusoe makes its own modules in Colorado. Amazon’s cut the fitting of a hall from 15 weeks to three.

Stick-builtModular
Ground to ready18 to 24 months12 to 18 months
Skilled hours, a MW12,0004,500
Cost, a MW$14.6 million$13.5 million
Share of capacity, 202869%31%

Month 0

The same hall, twice. Both break ground on the same day. One yellow dot is about ten workers.

Month 22: both are live

Eight months apart, for the same hall.

Modular: 21% this year, 31% by 2028

Its share of all capacity, on SemiAnalysis’s count. For the electricians to go round in 2027, about 60% of the work would have to be modular.

Who is betting on modular: Crusoe, Amazon, Fluidstack, Vertiv.

14 On site

Construction, in five stages

A data center is a low warehouse, simpler to put up than a high-rise. What takes the time, and the skilled hands, is the power and cooling that go in and around it. Scroll to build the first hall.

Electricians are what runs short: a third of all the hours on site, in a trade that takes four to five years to learn. The shortage does not stop the work. It raises the price of it.

Ground broken

The plan is still on the ground.

1 of 5: site work

Clear and level the land. Trench for power, water and fiber. Pour the slabs. The digging is shallow: no basement.

2 of 5: the shell

A steel frame, wall panels, a roof. This goes up fast.

3 of 5: the power yard

The substation, then transformers, switchgear, batteries and generators.

4 of 5: the cooling plant

Chillers outdoors, large pipes into the building, pump units feeding the racks.

5 of 5: fit-out

Cabling and piping to every rack position. Then the racks. The roof is lifted here only so you can see in.

Commissioning

A test at full load, before anyone pays rent.

Each hall at Crusoe’s Abilene campus, start to energising
roughly 10 months
What Crusoe raised wages by to staff it
30%

A designer, and three general contractors: Jacobs, DPR Construction, Turner, Holder.

15 The power path, grid to rack

Tiers: how much backup to build

Data centers are graded in four tiers, by how much can fail before the racks go dark. Each tier adds spare equipment, and then a whole second path.

A bank’s data center cannot stop. A hall training a model can: the job picks up from its last save. So some of the largest AI halls are built with less backup than the top tiers ask for, and the money goes into more megawatts.

From grid to rack

High voltage in. A transformer steps it down, switchgear routes it, batteries smooth it, and the rack takes it to under one volt at the chip.

Tier I

One path, and no spares.

Tier I: the transformer is out for repair

With one path and no spare, the racks go dark until it is back.

Tier II

Still one path, with a spare for each part that can be spared.

Tier II: a battery unit fails

The spare picks up its load. The racks stay on.

Tier III

A second path, standing by.

Tier III: the transformer is out for repair

Power takes the second path. Any one part can be serviced with the racks running.

Tier IV

Two paths, both live, each able to carry everything.

Tier IV: the switchgear fails without warning

Nothing changes. One fault cannot take the racks down.

Some AI halls build less

No generators, and a single feed. The saving buys more racks.

Downtime a year often quoted for Tier I
about 29 hours
And for Tier IV
about 26 minutes

A diagram of the idea. The Uptime Institute, which defines the tiers, no longer ties them to hours of downtime.

16 Hall by hall

Handover: one hall at a time

A site is secured for its full power and built in blocks, here 25 MW at a time. Each hall is tested at full load, handed over, and starts paying rent while the next one is going up.

Building in phases also shrinks what is at risk before a tenant signs. The land, the grid connection and the substation are still mostly paid for up front, for the whole site.

25 MW live

Hall 1 of 4 is handed over. Rent: $36 million a year.

50 MW live

Hall 2 of 4 is handed over. Rent: $72 million a year.

75 MW live

Hall 3 of 4 is handed over. Rent: $108 million a year.

100 MW live

All four halls are handed over. Rent: $144 million a year.

Abilene, by September 2026
6 of 8 buildings handed over

17 Taiwan to Texas

The chips: who gets them, who pays

Nvidia decides who gets its chips, and publishes no rule for how.

A hyperscaler pays cash for them. A neocloud, which owns chips and sells computing by the hour, borrows: and the price of its loan follows the customer behind the contract, not the chips.

Bottleneck 3: Chips, soon. Today the scarce thing is a powered building, and chips wait for one. From 2027 it turns round.

What is short
2025Buildings and power
Late 2026Powered sites. Chips wait
2027 to 2028Memory and the newest chips
End of 202810 GW of buildings too many

Chips, then racks: Nvidia, AMD, Foxconn, Quanta.

18 Inside one hall

Racks: power, coolant, network

A rack arrives built and tested: about 1.5 tonnes, drawing 135 kW. It is rolled into its row and joined to three things: power, coolant and the network.

There are two networks. Inside the rack, copper makes 72 GPUs act as one machine. Between racks, optical fiber runs through switches to join them into a cluster.

Every optical link needs a laser, and the lasers are short. So network gear, like the transformers, is ordered early.

A row with a gap in it

Power, coolant and fiber are already overhead, waiting.

A rack arrives

Built and tested at the factory: 72 GPUs, about 1.5 tonnes.

Power

About 50 volts DC on a metal bar down the back of the rack.

Coolant

A cold plate on every chip. Cool liquid in, warm liquid out.

The network

Copper inside the rack. Light between racks.

Nvidia’s commitment to each of two laser makers
$2 billion

Switches, then lasers: Arista, Celestica, Coherent, Lumentum.

19 The same hall

Testing, then switch-on

Before handover the hall is run at full load. Then the tenant’s own tests begin: every GPU is burned in, and the ones that fail go back.

About 15% of deployed Blackwell GPUs have had to be returned, and some clouds take six months to bring chips online. Speed here separates one operator from another.

When the hall passes, the rent starts.

Run at full load

The landlord proves the power and cooling before handing over.

Burn-in

The tenant runs every GPU flat out, and swaps the ones that fail.

Live

The hall passes. Rent starts today.

What a megawatt has to earn a year, by one test
about $20.4 million
The five-year market rate for a megawatt
$12 million to $16 million

20 The day it is sold

The profit: who takes what

The prize is one gap: a finished, leased building is worth more than it cost to build.

This one cost $1.13 billion. It earns $144 million a year in rent, and a buyer content with a 6.5% yield would pay $2.2 billion for it.

The loan is repaid first. The equity then earns 9% a year. What is left is split, with a 20% bonus share to the developer, called the promote. So the developer, who put in 2% of the money, takes 23% of the profit.

It cost $1.13 billion

The loan at the bottom, the equity on top.

Leased, it is worth $2.22 billion

$144 million a year of rent, sold at a 6.5% yield. The profit is $1.09 billion.

The lender: none of the profit

$735 million back, with its interest. It is paid first, and that is all it is paid.

The equity partner: 77% of the profit

$840 million, on $376 million put in. That is 3.2 times its money.

The developer: 23% of the profit

$250 million, on $20 million put in. It supplied 2% of the money.

The developer’s share of the profit
23%
With a costly build, lower rent and a 7.5% yield
the developer makes $31 million

An illustration on assumed terms. It leaves out running costs, interest during construction, fees and tax, so every figure is flattered. Not a forecast, and not financial advice.

Who does what

A data center is assembled from other people’s parts and other people’s money. Here are the leading companies at each seat, laid out the way things flow: down the page, converging on the developer, then on to whoever rents the building and whoever rents the compute.

Powered land

A site with its grid connection already in hand, assembled to sell or lease.

  • Tract (United States). Assembles land and power, then sells to developers. Privately held: Tract Capital, its founder's firm; launched in 2022 with Columbia Capital.
  • Primary Digital (United States). Co-owns the Abilene campus with Crusoe and Blue Owl. Privately held: Independent; founded in 2024 by four data centre industry veterans, ownership not disclosed.
  • Related Digital (United States). The data center arm of a large property developer. Privately held: Related Companies, the privately owned New York property developer.

In constrained markets this is now a business of its own. It is also among the first exposed if leasing slows.

Utilities

They own the lines, study the load, and commit megawatts on a date.

  • Dominion Energy (United States). Serves Northern Virginia, the largest market. Listed: NYSE: D.
  • American Electric Power (United States). Serves Ohio, Texas and nine other states. Listed: Nasdaq: AEP.
  • Entergy (United States). Serves Louisiana, home of Meta’s Hyperion. Listed: NYSE: ETR.
  • Sempra (Oncor) (United States). Owns Oncor, the largest Texas wires company. Listed: NYSE: SRE.

A grid connection in a primary market averages over four years.

Generators

Turbines, engines and fuel cells for a plant on the site.

  • GE Vernova (United States). Large and jet-derived gas turbines. Listed: NYSE: GEV.
  • Siemens Energy (Germany). Large gas turbines, and transformers. Listed: Xetra: ENR.
  • Mitsubishi Heavy (Japan). Large gas turbines. Listed: TSE: 7011.
  • Caterpillar (United States). Gas engines, and Solar turbines. Listed: NYSE: CAT.
  • Wärtsilä (Finland). Large gas engines. Listed: Nasdaq Helsinki: WRT1V.

Also: Bloom Energy, INNIO (Jenbacher), Bergen Engines, VoltaGrid, ProEnergy, Doosan Enerbility, Baker Hughes.

New large turbines ordered now deliver in 2030 or 2031, so builders use engines, fuel cells and refurbished jet-engine turbines.

Power gear

Transformers, switchgear, batteries and backup generators.

  • Schneider Electric (France). Switchgear, batteries and power distribution. Listed: Euronext Paris: SU.
  • Eaton (Ireland). Switchgear and power distribution. Listed: NYSE: ETN.
  • Vertiv (United States). Batteries, power distribution and cooling. Listed: NYSE: VRT.
  • ABB (Switzerland). Switchgear and transformers. Listed: SIX: ABBN.
  • Hitachi Energy (Japan). The largest maker of large transformers. Listed: TSE: 6501.

Also: Siemens, HD Hyundai Electric, Hyosung Heavy, LS Electric, Delta Electronics, Cummins, Rolls-Royce.

Quotes for transformers and switchgear run 52 to 150 weeks. The highest-voltage transformers take four to five years.

Cooling

Chillers outdoors, pump units indoors, cold plates on the chips.

  • Vertiv (United States). Pump units and chillers. Listed: NYSE: VRT.
  • Trane (Ireland). Chillers. Listed: NYSE: TT.
  • Carrier (United States). Chillers. Listed: NYSE: CARR.
  • Johnson Controls (Ireland). Chillers. Listed: NYSE: JCI.
  • nVent (United Kingdom). Pump units and manifolds. Listed: NYSE: NVT.

Also: Schneider Electric, CoolIT, Boyd Thermal, AVC, Auras.

Far less concentrated than chips: a capacity race, not a chokepoint.

Designers and builders

An engineering firm draws it. A general contractor builds it and hires the trades.

  • Jacobs (United States). Engineering and design. Listed: NYSE: J.
  • Burns & McDonnell (United States). Engineering and design. Privately held: Its employees.
  • DPR Construction (United States). General contractor. Privately held: Its employees.
  • Turner (United States). General contractor. Privately held: Hochtief.
  • Holder (United States). General contractor. Privately held: Privately held.

Also: Black & Veatch, Mortenson, Rosendin, Quanta Services, EMCOR.

The labor limit is electricians: the trade takes four to five years to train.

Equity

Infrastructure funds. They put up the risky early money and take most of the ownership.

  • Blackstone (United States). Owns QTS. Listed: NYSE: BX.
  • Brookfield (United States). Backs Compass. Listed: NYSE: BAM.
  • KKR (United States). Owns CyrusOne, with GIP. Listed: NYSE: KKR.
  • BlackRock (United States). Owns 80% of Meta’s El Paso campus. Its GIP led the purchase of Aligned. Listed: NYSE: BLK.
  • Blue Owl (United States). Owns 80% of Meta’s Hyperion campus. Listed: NYSE: OWL.

Also: DigitalBridge, Macquarie, MGX, SoftBank.

Developers typically spend only 5% to 10% of project capital before a tenant signs.

Lenders

Banks and private credit. Most of the build cost, lent against the lease and paid back first.

  • JPMorgan (United States). Lent $9.4 billion to build Abilene. Listed: NYSE: JPM.
  • Morgan Stanley (United States). Arranged Hyperion’s $27.3 billion of bonds. Listed: NYSE: MS.
  • MUFG (Japan). Led, with JPMorgan, $38 billion for two Oracle campuses. Listed: TSE: 8306.
  • Apollo (United States). Private credit. Leases chips to Anthropic and SpaceX. Listed: NYSE: APO.
  • PIMCO (United States). Bought about $18 billion of Hyperion’s bonds. Privately held: Allianz.

Also: Goldman Sachs, SMBC, Ares, Magnetar.

A pre-leased building borrows 60% to 80% of its cost. The lender’s money arrives fifth, after the tenant signs.

Developers and landlords

They find the site, secure the power, sign the tenant and own the building.

  • Digital Realty (United States). Landlord at scale: 1.2 GW under construction. Listed: NYSE: DLR.
  • Equinix (United States). Landlord at scale. Listed: Nasdaq: EQIX.
  • QTS (United States). Builds for hyperscalers. Privately held: Blackstone funds (Blackstone Infrastructure Partners and BREIT).
  • Vantage (United States). Building 1.4 GW in Texas for Oracle and OpenAI. Privately held: Investor group led by DigitalBridge (now part of SoftBank) and Silver Lake.
  • Aligned (United States). Bought for about $40 billion in July 2026. Privately held: The AI Infrastructure Partnership (AIP), MGX and BlackRock's Global Infrastructure Partners.

Also: Stack Infrastructure, CyrusOne, Compass, Switch, DataBank.

Mostly owned by private funds, who are also a new developer’s likely partners and buyers.

Chips and racks

The larger part of the bill, bought by the tenant and delivered as finished racks.

  • Nvidia (United States). Designs the GPUs and the rack. Listed: Nasdaq: NVDA.
  • AMD (United States). Designs GPUs. Listed: Nasdaq: AMD.
  • Broadcom (United States). Designs custom chips for Google and others. Listed: Nasdaq: AVGO.
  • Foxconn (Taiwan). Builds the racks. Listed: TWSE: 2317.
  • Quanta (Taiwan). Builds the racks. Listed: TWSE: 2382.

Also: Wiwynn, Supermicro, Dell, HPE.

Nvidia decides who gets supply, and publishes no rule for how. The five largest American buyers took about 70% of its racks in 2025.

Network

Switches, and the optics and fiber that join racks into a cluster.

  • Arista (United States). Switches. Listed: NYSE: ANET.
  • Cisco (United States). Switches. Listed: Nasdaq: CSCO.
  • Celestica (Canada). Builds switches for others. Listed: NYSE: CLS.
  • Innolight (China). Optical modules. Listed: SZSE: 300308.
  • Coherent (United States). Lasers and optical modules. Listed: NYSE: COHR.

Also: Eoptolink, Lumentum, Corning, Amphenol, Credo.

Every optical link needs a laser, and the lasers are short.

Neoclouds

They own the chips, rent the building or build it, and sell compute.

  • CoreWeave (United States). Chips first. 1.7 GW live, 4.6 GW contracted. Listed: Nasdaq: CRWV.
  • Crusoe (United States). Power first. Over 6 GW contracted. Privately held: Founders, staff and investors including Valor, Mubadala Capital and Atreides.
  • Nebius (Netherlands). Out of Yandex’s Dutch parent. Over 4 GW contracted. Listed: Nasdaq: NBIS.
  • Lambda (United States). Leases its space. Microsoft and Nvidia are customers. Privately held: Founders, staff and investors including Nvidia.
  • Nscale (United Kingdom). British. Filed in September 2026 to list in New York. Privately held: Founders and investors including Aker, 8090 Industries and Nvidia.

Also, several of them former bitcoin miners: Fluidstack, IREN, Applied Digital, Core Scientific, TeraWulf, Cipher, Galaxy, Firmus.

The pattern across them: a handful of customers, a great deal of debt, and power as the thing that slips.

Hyperscalers

The tenants lenders like best. They sign the lease and bring their own chips.

  • Microsoft (United States). Rated Aaa and AAA. Listed: Nasdaq: MSFT.
  • Alphabet (Google) (United States). Rated Aa2 and AA+. Listed: Nasdaq: GOOGL.
  • Amazon (United States). Rated A1 and AA. Listed: Nasdaq: AMZN.
  • Meta (United States). Rated Aa3 and AA−, outlook negative. Listed: Nasdaq: META.
  • Oracle (United States). Rated Baa2 and BBB−, one step above junk. Listed: NYSE: ORCL.

In 2026 their capital spending passes $800 billion and exceeds their operating cash flow for the first time.

Labs

The end of the chain. They mostly rent compute from the two groups above, and own nothing here.

  • OpenAI (United States). Rents from Oracle, Microsoft, CoreWeave and others. Privately held: OpenAI Foundation (non-profit), Microsoft, SoftBank, staff and other investors.
  • Anthropic (United States). Rents from Amazon, Google and Microsoft, and through Fluidstack. Listed: Nasdaq: ANT.
  • xAI (United States). The exception: SpaceX builds its own. Privately held: SpaceX (Nasdaq: SPCX).

Anthropic’s listing papers set out about $895 billion of compute and infrastructure commitments.

Who keeps the money

23% of the bill for 100 MW is the building, with all its power and cooling: about $1.1 billion of $4.9 billion. The other 77% is chips and servers.

75% is Nvidia’s gross margin: the largest single slice of every dollar spent here. A neocloud on a five-year contract earns a return of about 16% a year.

2% in, 23% out In the worked example the developer supplies 2% of the money and takes 23% of the profit. Before a tenant signs, only 5% to 10% of the project’s capital is at risk.

2.25 or 5.5 points over the benchmark rate: what one borrower, CoreWeave, pays on chip loans backed by Meta’s contract and by unrated customers’. The price follows the tenant.