01 The United States
Data centers go where the power is
A data center is built wherever electricity can be had on a date. Land is easy. A hundred megawatts, as much as a small city draws, is not.
You cannot rent your way there. Northern Virginia, the largest market in the world, had 10.8 MW left to lease in the first half of 2026.
Northern Virginia is full
The largest data center market in the world, with 10.8 MW left to lease. A new campus wants ten times that.
So it goes where the power is
The campus lands wherever 100 MW can be had on a date. Here, west Texas.
The largest campuses now going up
Not one of them is in an old data center market.
- Left to lease in Northern Virginia, first half of 2026
- 10.8 MW
- A grid connection in a primary market takes
- over four years
Who needs the megawatts: Microsoft, Alphabet (Google), Amazon, Meta, Oracle.
02 A field, somewhere with power
What a 100 MW site needs
Five things, in one place. The search starts from a map of power lines, not a map of land: utilities publish how much room their lines have, and grid operators publish who is already waiting.
The commonest shortcut is an old industrial site, which already has a substation and a connection. This one is a field with all five. Scroll down the list.
- Land: 50 to 100 acres. Half an acre to an acre for every megawatt, going by the largest campuses. This field is 130 acres, which leaves room to grow.
- Power: 125 MW. To run 100 MW of racks a site draws about 125 MW, as much as a small city. That takes a high-voltage line with room to spare, and a substation of your own.
- Gas: 25 million cubic feet a day. Only if the site will make its own power. A plant this size burns about 25 million cubic feet a day, so it needs a large pipeline close by, with that much to spare.
- Fiber: two separate routes. Long-haul cable, which tends to follow roads and railways. Distance hardly matters: a model in training does not care how far away it is.
- Water: little. Less than most people think. The loop that cools the chips is filled once and sealed, so the creek matters most as a flood line to build clear of.
- Cash to hold a site like this while it is checked
- a few million dollars
- What gets built on it, chips included
- about $4.9 billion
The site is invented, to show the parts. They are drawn the size real ones are.
03 The same field
Audit the site: eight checks
A site is put to eight questions, in the order they most often end a deal. If the first two hold, most of the rest can be solved.
- The power is real. A written commitment from the utility, with megawatts and a date. Lenders underwrite exactly this.
- The land can be controlled. And zoning allows a data center on it.
- The community will not fight it. Check for talk of a moratorium before spending money.
- Water and cooling. The loop that cools the chips is filled once and sealed. Water is only used up if heat is shed outdoors by evaporation, so ask how this site will shed it.
- Fiber. Large routes nearby, or a cheap way to bring them in.
- The ground. No flood zone, soil that carries heavy buildings, room to grow.
- Labor. Electricians and contractors within reach.
- Money terms. The price of power, tax breaks, and who pays for grid upgrades.
04 The landowner’s kitchen table
Reserve the land with an option
The usual move is to pay the owner a fee to hold the site for a year or two, with the right to buy at an agreed price. In that window the checks are run. If one fails, the developer walks away and loses only the fee.
The paper comes in three steps: a confidentiality agreement, a one-page letter of intent that binds nobody, then the option itself.
A landowner who knows what the site is worth may prefer a long ground lease, or a share of the income, to a single payment.
05 The utility, and the grid operator
Get the power committed in writing
A site is worth what its signed, dated utility agreement says. First the utility studies whether its lines and substations can carry the load, for a fee. Then it commits megawatts and a date.
Texas asks at least $100,000 for the study, and proposes $50,000 a megawatt of security on top.
Then comes the queue. Texas has about 474 GW of requests waiting, roughly nine-tenths of them data centers.
Bottleneck 1: Power on a date. A grid connection in a primary market takes over four years on average.
- Waiting to connect in Texas
- about 474 GW
- Security before the study, at 100 MW
- about $5 million
06 Back on the site
Power: the grid, or your own plant
There are two routes to 100 MW. Many projects take both: gas first, as a bridge, and the grid later.
From 2028, SemiAnalysis expects over half of new American data centers to make their own power. In 2025 it was under 7%.
| The grid | Your own plant |
|---|
| The wait | Over four years | About two |
|---|
| Power costs, a MWh | $55 to $115 | $100 to $165 |
|---|
| Tight spot | Big transformers | Turbines, air permit |
|---|
The plan, on the ground
Four halls of 25 MW. Now for where the power comes from.
Route A: the grid
Build a substation and tap the line. The cheapest power there is, after a long wait.
Route B: make it yourself
A row of gas engines and a bank of batteries. Faster, and dearer.
Often both
Gas first, as a bridge. The grid later.
Who makes the generators: GE Vernova, Siemens Energy, Wärtsilä, Bloom Energy.
07 County hall, then the state capital
Permits: who has to say yes
Even off the grid, several parties must give permission. Making your own power saves only the utility’s queue.
- The county or city: zoning. Is a data center allowed on that land at all? Most fights happen here.
- The county again: building and electrical permits. With inspections before anything is switched on.
- The state: an air permit. If gas is burned on site. Often the slowest of the five.
- Water. If the cooling uses it.
- The pipeline company. To connect the site and guarantee the fuel.
- Local ballot measures on data centers, 3 November 2026
- 40 of 41 went against them
Rules differ by state and county. This is a map, not legal advice.
08 The deal
The deal: six parties, in order
A newcomer brings one thing, the powered site. Everyone else brings money, and the lender’s arrives fifth.
- Lock up the site and the power. With an option. It is cheap, and it is the developer’s whole stake.
- Bring in an equity partner. Usually an infrastructure fund. It puts up the risky early money, and takes most of the ownership.
- Spend the early money. Utility deposits, equipment deposits to hold a delivery slot, engineering, permits. Typically 5% to 10% of the project’s capital.
- Sign the tenant. One lease, for the whole site or a large phase.
- Close the construction loan. The equity goes in first. The lender releases money in stages as work is inspected.
- Build, test, hand over. Hall by hall. Rent starts with each handover.
- Refinance, or sell. Into cheaper long-term debt, or to a buyer.
Abilene, Texas: 1.2 GW, for OpenAI
- Landowner: Lancium, which also manages the power
- Developer: Crusoe
- Equity partner: Blue Owl and Primary Digital
- Tenant: Oracle, renting it on to OpenAI
- Lender: JPMorgan: $9.4 billion of loans
- Builders: Crusoe, which builds its own
Hyperion, Louisiana: 2 GW at first, for Meta
- Developer: Meta itself
- Equity partner: Blue Owl, which owns 80%
- Tenant: Meta, on four-year terms it can walk from
- Lender: Bond buyers: $27.3 billion at 6.58%, to 2049
River Bend, Louisiana: 245 MW, for Anthropic
- Developer: Hut 8, a former bitcoin miner
- Tenant: Fluidstack, renting it on to Anthropic
- Lender: Bond buyers: $3.25 billion at 6.19%
- Backstop: Google, which guarantees the rent
Polaris Forge, North Dakota: 400 MW, for CoreWeave
- Developer: Applied Digital, once a host for bitcoin miners
- Equity partner: Macquarie: $5 billion, at 12.75% plus 15% of it
- Tenant: CoreWeave: about $11 billion over 15 years
Frontier, Texas: 1.4 GW, for OpenAI
- Developer: Vantage
- Tenant: Oracle, renting it on to OpenAI
- Lender: JPMorgan and MUFG: $38 billion, with a sister site
- Builders: Among them Jenbacher: over 500 gas engines
Childress, Texas: 750 MW, for Microsoft
- Landowner: IREN
- Developer: IREN, once a bitcoin miner. It owns the chips too
- Tenant: Microsoft: $9.7 billion over five years, 20% up front
09 One contract
The lease: rent by the kilowatt
One tenant usually leases the whole site, or a large phase of it, before anything is built. That signed lease is what a lender will lend against.
It rents power, not floor space: about $100 to $150 for every kilowatt it reserves, every month, for 10 to 15 years, rising about 3% a year.
The landlord provides the building, the power and the cooling. The tenant brings its own chips, and pays the electricity bill on top.
Signed, before anything is built
No rent yet. It starts when the first hall is handed over.
Year 1: $144 million
Twelve months of rent.
15 years: $2.7 billion
The pale bars are what the building cost: the first seven years of rent pay for it. The lease is worth 2.4 times the building.
- In Northern Virginia, asking, a kilowatt a month
- $160 to $185
Who signs, most often: Microsoft, Amazon, Oracle, Meta.
10 The bill for 100 MW
The cost: 23% building, 77% chips
The building, with all its power and cooling gear, averages $11.3 million a megawatt in 2026: about $1.1 billion for 100 MW.
The racks that fill it cost about $3.7 billion more. So of every $4 spent, about $1 goes on the building and $3 on the chips inside it. A different party usually pays for them.
$1.13 billion: the building
With all its power and cooling gear. 113 blocks.
$3.74 billion: what goes inside
740 racks of chips and servers. 374 blocks, and usually someone else’s money.
23% building, 77% chips
Of every $4 spent, about $1 is the building and $3 is the chips inside it.
- The building’s share of the whole bill
- 23%
- Chips and servers, per MW
- about $37 million
- Electrical work’s share of the building
- 45% to 70%
One block is $10 million.
11 The lender’s office
The loan: 65% of the building
With the lease signed, a lender will cover 60% to 80% of the building’s cost: here 65%. The equity partner puts in 33% and the developer 2%. The loan runs 12 to 36 months, and is made to a company set up only to own this project.
Lenders check three things: the tenant’s credit, the utility’s written commitment, and whether the switch-on date is realistic.
$1.13 billion to find
The building, before a single chip.
65%: the loan
$735 million, lent against the lease. It is paid back first.
33%: the equity partner
$376 million from an infrastructure fund. It goes in before the lender’s money does.
2%: the developer
$20 million of its own cash. What it really brings is the site.
Meta’s way: 90% borrowed
Its Hyperion campus cost about $30 billion. A company owned 80% by Blue Owl borrowed $27 billion of it, and Meta rents the campus back.
- Borrowed for Meta’s Hyperion campus
- 90%
Banks that arrange the loans: JPMorgan, Morgan Stanley, MUFG, Goldman Sachs.
12 A calendar, from today
Order the equipment years ahead
The building is quick. The equipment is not. So the developer orders the slow parts itself, before the contractor is even hired.
Suppose all of it is ordered today. Scroll to see when each thing arrives.
Bottleneck 2: The slow equipment. Money cannot hurry it: a deposit only holds a place in a factory’s queue.
Ordered today
Everything on this floor is ordered on the same day, at the end of 2026.
Who makes the slowest of it: Hitachi Energy, Siemens Energy, GE Vernova, Schneider Electric, Eaton.
The waits are the middle of the ranges quoted in 2026. The building’s is for one built the usual way.
13 Two halls, started the same day
Modular: built in a factory
The usual way, called stick-built, fits every part by hand on site. A modular data center is built in a factory, as finished sections of power, cooling and rack space, and trucked in.
Crusoe makes its own modules in Colorado. Amazon’s cut the fitting of a hall from 15 weeks to three.
| Stick-built | Modular |
|---|
| Ground to ready | 18 to 24 months | 12 to 18 months |
|---|
| Skilled hours, a MW | 12,000 | 4,500 |
|---|
| Cost, a MW | $14.6 million | $13.5 million |
|---|
| Share of capacity, 2028 | 69% | 31% |
|---|
Month 0
The same hall, twice. Both break ground on the same day. One yellow dot is about ten workers.
Month 22: both are live
Eight months apart, for the same hall.
Modular: 21% this year, 31% by 2028
Its share of all capacity, on SemiAnalysis’s count. For the electricians to go round in 2027, about 60% of the work would have to be modular.
Who is betting on modular: Crusoe, Amazon, Fluidstack, Vertiv.
14 On site
Construction, in five stages
A data center is a low warehouse, simpler to put up than a high-rise. What takes the time, and the skilled hands, is the power and cooling that go in and around it. Scroll to build the first hall.
Electricians are what runs short: a third of all the hours on site, in a trade that takes four to five years to learn. The shortage does not stop the work. It raises the price of it.
Ground broken
The plan is still on the ground.
1 of 5: site work
Clear and level the land. Trench for power, water and fiber. Pour the slabs. The digging is shallow: no basement.
2 of 5: the shell
A steel frame, wall panels, a roof. This goes up fast.
3 of 5: the power yard
The substation, then transformers, switchgear, batteries and generators.
4 of 5: the cooling plant
Chillers outdoors, large pipes into the building, pump units feeding the racks.
5 of 5: fit-out
Cabling and piping to every rack position. Then the racks. The roof is lifted here only so you can see in.
Commissioning
A test at full load, before anyone pays rent.
- Each hall at Crusoe’s Abilene campus, start to energising
- roughly 10 months
- What Crusoe raised wages by to staff it
- 30%
A designer, and three general contractors: Jacobs, DPR Construction, Turner, Holder.
15 The power path, grid to rack
Tiers: how much backup to build
Data centers are graded in four tiers, by how much can fail before the racks go dark. Each tier adds spare equipment, and then a whole second path.
A bank’s data center cannot stop. A hall training a model can: the job picks up from its last save. So some of the largest AI halls are built with less backup than the top tiers ask for, and the money goes into more megawatts.
From grid to rack
High voltage in. A transformer steps it down, switchgear routes it, batteries smooth it, and the rack takes it to under one volt at the chip.
Tier I
One path, and no spares.
Tier I: the transformer is out for repair
With one path and no spare, the racks go dark until it is back.
Tier II
Still one path, with a spare for each part that can be spared.
Tier II: a battery unit fails
The spare picks up its load. The racks stay on.
Tier III
A second path, standing by.
Tier III: the transformer is out for repair
Power takes the second path. Any one part can be serviced with the racks running.
Tier IV
Two paths, both live, each able to carry everything.
Tier IV: the switchgear fails without warning
Nothing changes. One fault cannot take the racks down.
Some AI halls build less
No generators, and a single feed. The saving buys more racks.
- Downtime a year often quoted for Tier I
- about 29 hours
- And for Tier IV
- about 26 minutes
A diagram of the idea. The Uptime Institute, which defines the tiers, no longer ties them to hours of downtime.
16 Hall by hall
Handover: one hall at a time
A site is secured for its full power and built in blocks, here 25 MW at a time. Each hall is tested at full load, handed over, and starts paying rent while the next one is going up.
Building in phases also shrinks what is at risk before a tenant signs. The land, the grid connection and the substation are still mostly paid for up front, for the whole site.
25 MW live
Hall 1 of 4 is handed over. Rent: $36 million a year.
50 MW live
Hall 2 of 4 is handed over. Rent: $72 million a year.
75 MW live
Hall 3 of 4 is handed over. Rent: $108 million a year.
100 MW live
All four halls are handed over. Rent: $144 million a year.
- Abilene, by September 2026
- 6 of 8 buildings handed over
17 Taiwan to Texas
The chips: who gets them, who pays
Nvidia decides who gets its chips, and publishes no rule for how.
A hyperscaler pays cash for them. A neocloud, which owns chips and sells computing by the hour, borrows: and the price of its loan follows the customer behind the contract, not the chips.
Bottleneck 3: Chips, soon. Today the scarce thing is a powered building, and chips wait for one. From 2027 it turns round.
| What is short |
|---|
| 2025 | Buildings and power |
|---|
| Late 2026 | Powered sites. Chips wait |
|---|
| 2027 to 2028 | Memory and the newest chips |
|---|
| End of 2028 | 10 GW of buildings too many |
|---|
Chips, then racks: Nvidia, AMD, Foxconn, Quanta.
18 Inside one hall
Racks: power, coolant, network
A rack arrives built and tested: about 1.5 tonnes, drawing 135 kW. It is rolled into its row and joined to three things: power, coolant and the network.
There are two networks. Inside the rack, copper makes 72 GPUs act as one machine. Between racks, optical fiber runs through switches to join them into a cluster.
Every optical link needs a laser, and the lasers are short. So network gear, like the transformers, is ordered early.
A row with a gap in it
Power, coolant and fiber are already overhead, waiting.
A rack arrives
Built and tested at the factory: 72 GPUs, about 1.5 tonnes.
Power
About 50 volts DC on a metal bar down the back of the rack.
Coolant
A cold plate on every chip. Cool liquid in, warm liquid out.
The network
Copper inside the rack. Light between racks.
- Nvidia’s commitment to each of two laser makers
- $2 billion
Switches, then lasers: Arista, Celestica, Coherent, Lumentum.
19 The same hall
Testing, then switch-on
Before handover the hall is run at full load. Then the tenant’s own tests begin: every GPU is burned in, and the ones that fail go back.
About 15% of deployed Blackwell GPUs have had to be returned, and some clouds take six months to bring chips online. Speed here separates one operator from another.
When the hall passes, the rent starts.
Run at full load
The landlord proves the power and cooling before handing over.
Burn-in
The tenant runs every GPU flat out, and swaps the ones that fail.
Live
The hall passes. Rent starts today.
- What a megawatt has to earn a year, by one test
- about $20.4 million
- The five-year market rate for a megawatt
- $12 million to $16 million
20 The day it is sold
The profit: who takes what
The prize is one gap: a finished, leased building is worth more than it cost to build.
This one cost $1.13 billion. It earns $144 million a year in rent, and a buyer content with a 6.5% yield would pay $2.2 billion for it.
The loan is repaid first. The equity then earns 9% a year. What is left is split, with a 20% bonus share to the developer, called the promote. So the developer, who put in 2% of the money, takes 23% of the profit.
It cost $1.13 billion
The loan at the bottom, the equity on top.
Leased, it is worth $2.22 billion
$144 million a year of rent, sold at a 6.5% yield. The profit is $1.09 billion.
The lender: none of the profit
$735 million back, with its interest. It is paid first, and that is all it is paid.
The equity partner: 77% of the profit
$840 million, on $376 million put in. That is 3.2 times its money.
The developer: 23% of the profit
$250 million, on $20 million put in. It supplied 2% of the money.
- The developer’s share of the profit
- 23%
- With a costly build, lower rent and a 7.5% yield
- the developer makes $31 million
An illustration on assumed terms. It leaves out running costs, interest during construction, fees and tax, so every figure is flattered. Not a forecast, and not financial advice.